🇩🇪 German Engineering Precision • 100% Watertight & Maintenance-Free • 30-Year Manufacturer Warranty
Home » Assembly & Installation Instructions

Assembly & Installation Instructions

Follow our standardized step-by-step engineering guidelines for installing AVA Aluminium Decking Profile S (13 mm) and Profile L (40 mm). With the patented Safe-Clickâ„¢ tongue-and-groove joint, assembly is rapid, error-free, and requires no specialized tools.

Official Assembly Manual (PDF)

Download the complete 16-page illustrated technical manual for offline job-site reference.

Download PDF Manual (3.2 MB) →

SECTION 01

Workplace Health & Personal Safety

Professional job execution requires strict adherence to workplace safety standards. Please wear appropriate personal protective equipment (PPE) during all fabrication and cutting stages:

🥾
Sturdy Safety Footwear
Steel-toe work shoes
🧤
Cut-Resistant Gloves
Handling extruded profiles
🥽
Safety Goggles
Protection against metal shavings
🎧
Hearing Protection
When operating miter saws

SECTION 02

Required Standard Hand & Power Tools

  • Miter Saw / Circular Saw: Equipped with a carbide-tipped negative-rake blade formulated specifically for non-ferrous metals.
  • Cordless Drill / Screwdriver: With magnetic bit holder and Torx TX20 bits for stainless steel fasteners.
  • Rubber Mallet: Non-marking white rubber mallet for snapping the Safe-Clickâ„¢ locking flange smoothly into place.
  • Spirit Level & Measuring Tape: To verify uniform substructure alignment and minimum 1.5% drainage slope.
  • Cordless Vacuum or Hand Broom: To remove all aluminium filings from the decking surface immediately after cutting.

SECTION 03

Substructure Engineering & Joist Spacing

The sub-frame must provide an unyielding, structurally sound base aligned perpendicular to the decking direction:

AVA Profile S (13 mm)

Maximum center-to-center joist span: 500 mm (0.50 m). For high public commercial loads, reduce spacing to 400 mm.

Minimum Drainage Slope: 1.5%

AVA Profile L (40 mm)

Maximum center-to-center joist span: 800 mm (0.80 m). High section modulus withstands 5.0 kN/m² without deflection.

Minimum Drainage Slope: 1.5%

SECTION 04

Step-by-Step Assembly Procedure

1

Apply Kompriband Decoupling Tape

Affix elastomeric compression tape along the top surface of all substructure beams to provide acoustic impact deadening and galvanic separation.

2

Secure the Starter Edge Profile (Antrittskante)

Anchor the starter profile along the outer edge with stainless steel self-drilling fasteners. This creates the concealed receptor groove for the first decking plank.

3

Insert the First Plank & Fasten the Rear Flange

Slide the front tongue into the starter profile. Fasten the integrated rear flange to each substructure joist using 2 screws per intersection.

4

Engage Subsequent Planks with Safe-Clickâ„¢ Locking

Hook the next profile’s tongue into the previous profile’s receiver. Tap lightly with a non-marking rubber mallet along the joint until an audible click confirms hermetic engagement.

5

Mount Water Gutter and Fascia Trim

Clip the integrated drainage gutter kit onto the discharge edge and seal end caps with Otto Seal A250 adhesive. Attach frontal cover angle trims for clean perimeter aesthetics.

Calculate Material in Configurator →
Type-Tested
Type-Tested Statics Certified for 4–5 kN/m² surface loads
Safe-Click
100% Watertight Patented Safe-Click Joint System
R11 Slip Resistance
R11 Anti-Slip Surface DIN 51130 certified for wet zones
30 Years Warranty
30-Year Warranty Extremely durable & corrosion-free